Description
For
the ideal economical treatment of interior
walls and ceilings dry-distemper imparts
solid decorative finish to them.
Mixing
To
moderate hot water, powder is added gradually
under constant stirring until a stiff paste
is formed. Allow the pate to stand for about
30 minutes and then thin it to the consistency
with water.
Surface
Preparation
Surface
should be sand papered down and all the
other surface defects like cracks holes
etc. should be made good with plaster and
allowed to dry off before the surface is
washed clean & free from Dust and Grease.
Application
It
is to be applied evenly with a good distemper
brush. During application period distemper
should be stirred from time to time. For
very absorbent surface a coat of glue size
is recommended.
Drying
Time
Approximately
6 hr.
Packing
1.5
Kgs. & 20 Kgs.
Covering
Capacity
9
to 12 sq. meters per Kg. depending on surface.
|